ABB COMMANDER 1911 Operating Manual page 30

Circular chart recorders. controller versions
Table of Contents

Advertisement

...5 CONTROL OPERATION
...5.9 Introduction to Standard Control
Decrease Proportional Band
Response Time
Time
28
Initial Settings
Proportional Band = 100%
Integral Action Time = OFF
Derivative Action Time = OFF
Adjust the set point a small amount
Hold the set point at the new value until
the process begins to move
Reset the set point to the original valuee
Observe response of process
Response Time
Critical
Cycle time (tcc
Note Proportional Band value (PBc)
Measure the critical cycle time (tc)
Calculate Terms
P
P+I
P
2 x PBc
2.2 x PBc
I
tc/1.2
D
Fig. 5.17 Manual Tuning
P+D
P+I+D
1.6 x PBc
1.6 x PBc
tc/2
tc/2
tc/12
tc/8
Increase Proportional Band
Response Time
Time