Basic physical installation
Below is a list of basic steps necessary to properly install LWT series instruments, as recommended by
ABB. All installations should be performed by certified and authorized personnel in accordance with all
applicable local security codes (electrical, engineering, etc.) (the page references in parentheses refer to
the LWT series user's guide)
Here are the basic installation steps:
1 Access and properly secure the installation site (vessel depressurization and cool down, mains power
down, etc.).
2 Attach the probe to the head/coupler assembly.
3 Slide the probe in the vessel and attach the probe/coupler assembly on the flange.
4 Connect the mains to the head unit.
5 Power up and configure the instrument.
Simple connection diagram
Here is a simple power connection diagram for LWT series instruments.
Figure 2
Typical LWT connection
Initial software setup
Initial setup of the instrument is performed via the Easy Setup menu. Below you will find menu items,
factory-set values and lists of all available values when you click Select from the Easy Setup screen.
Figure 3
Easy Setup menu