NetEco 6000 V600R008C00 Device Installation and Commissioning Guide Issue Date 2019-03-10 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
For details about southbound devices connected to the NetEco that are not described in this document, see iManager NetEco V600R007C90 Device Installation and Commissioning Guide. For details about NetEco product software commissioning, see iManager NetEco 6000 V600R008C00 Product Documentation. The figures provided in this document are for reference only.
1.1 General Safety Precautions This section describes safety precautions for installing, operating, and maintaining a smart module. Declaration Huawei will not be liable for any consequences of the following scenarios: Running in conditions not specified in this manual. ...
Only trained and qualified personnel are allowed to remove safety facilities and inspect the equipment. Only personnel certified or authorized by Huawei are allowed to replace or change the equipment or components (including software). Installation personnel must report faults or errors that might cause serious safety issues to related owners.
NetEco 6000 Device Installation and Commissioning Guide 2 Installation Preparations Huawei will not be liable for any consequence caused by the violation of this document. The requirements are as follows: Customers' installation personnel must be trained by Huawei and understand how to install and operate a Smart Module.
Procedure Step 1 For details about how to connect monitoring cables to the ECC800, see the Intelligent Micro-Module Management System Wiring Diagram, visit http://e.huawei.com/, search for Smart Modular Data Center Quick Reference Guide and download it. The onsite wiring diagram of the management system prevails. The method described in this section is for reference only.
NetEco Software Installation and Commissioning Guide. For single-server scenarios, see the iManager NetEco 6000 Product Documentation. For double-server scenarios, see the iManager NetEco 6000 High Availability System Product Documentation. Table 6-1 Encryption algorithms...
The camera IP address and the VCN service IP address must be in the same network segment. For details about northbound IP address, see section Overview of Southbound and Northbound Network Isolation in iManager NetEco 6000 Product Documentation. 6.3.2.1 Configuring VCN500 Server Parameters 6.3.2.1.1 Changing IP Addresses of VCN500 Servers Context A default IP address is configured for a VCN500 server before delivery.
Page 165
Restart Internet Explorer and enter the IP address to be accessed by the client. The page for watching videos is displayed. Click Install according to the prompt message. After the OCX plug-in is installed, you can watch the videos. If videos are not displayed, contact Huawei technical support.
The NetEco system provides a Huawei-preinstalled default certificate for commissioning the connections between network elements and the NetEco. The default certificate cannot ensure information transmission security, and must be replaced by a valid certificate from Huawei if the secure communication mode is to be enabled.
NetEco 6000 Device Installation and Commissioning Guide 7 Device Maintenance Follow-up Procedure If the hard disk works abnormally, contact Huawei technical support. 7.2.6.3 Replacing an IPC6325 Camera Prerequisites The camera needs to be replaced. A spare camera of the same model is available and functional.