Step 2 Insert the optional BSC card into the control module in Huawei's UPS and secure the card.
Step 3 Verify that the output side of other vendor's UPS is de-energized. Then connect the sampling
cable and signal cables to the BSC card.
Figure 3-2 Connecting the BSC card
(1) Signal cable
Step 4 Power on Huawei's UPS and energize the output side of other vendor's UPS. Check that only
the POWER indicator on the BSC card is on.