Download Print this page

Huawei OptiX OSN 6800 Quick Installation Manual page 7

Intelligent optical transport platform, n63b cabinet
Hide thumbs Also See for OptiX OSN 6800:

Advertisement

Installing Subracks and Boards
1
1 Installing Subracks(Subracks and Single DCM Frame)
NOTE
Remove the front door and side doors of the cabinet before routing cables. For details on how to remove the
N63B Cabinet Installation Guide
doors, see the
NOTE
For safety concern, at least two persons are required to install a subrack. One person is to hold the subrack and
the other person to tighten the panel screws.
83
81
77
76
OptiX OSN 6800
63
62
61
60
OptiX OSN 6800
47
46
Air deflector
40
37
36
35
OptiX OSN 6800
22 21
20
19
OptiX OSN 6800
6
5
3
2
.
Front
PDU
Subrack 4
Subrack 3
Subrack 2
Subrack 1
DCM
Cabinet
column
Panel screw
Place the the subrack onto the column guide rails inside the
cabinet.
Secure the subrack on the cabinet columns with panel screws.
4
Installation
Structural
holes on one
component
column
DCM frame
2, 3
Subrack 1
5, 6, 19, 20
Subrack 2
21, 22, 35, 36
Air deflector
37, 40
Subrack 3
46, 47, 60, 61
Subrack 4
62, 63, 76, 77
TN11PDU
79, 83
DPD63-4-8
81, 83
PDU