Figure 40: Measurements View - ABB UniGear Digital Commissioning And Testing Manual

Hide thumbs Also See for UniGear Digital:
Table of Contents

Advertisement

CU R R E N T S EN SO R S
Step 6/7
Check current metering for the phase and measured current in other phases on the protec-
tion relay LHMI Measurements view.
Current must be zero in phases which are not under the primary injection test.

Figure 40: Measurements view

"Io-A" in Measurements view is a measured value, not a calculated one.
Step 7/7
After testing of all 3 phases, install the back-overpressure relief flap. Set up the Ith limiter and
verify its function in the switchgear panel.
Protection functions trip the signal block Tripping coil supervision function.
2 8
PR IM AR Y T EST IN G
1 VLG 5000 17 C