Huawei UPS5000-H Series Quick Manual page 2

Hide thumbs Also See for UPS5000-H Series:

Advertisement

Installing Cabinets and Cables(800 kVA)
01
Unpacking
Space Planning
Securing the Cabinet
unit: mm
A: mounting holes on the channel steel
B: mounting holes on the floor
UPS5000-H-(400 kVA-800 kVA) Quick Guide (100 kVA Power Modules)
M12 bolt
Spring washer
Flat washer
Concrete floor
Expansion sleeve
Expansion nut
02
全局信息
Installing Cables
Battery
input
Cables of the same group, for example, mains input
cables, must be routed through the same cable hole.
Different power sources are used as an example.
The number and color of signal cables in the figure
are for reference only.
Power
modules
02
Verifying the Installation
1. Check that there is no foreign matter in the cabinets.
2. (Remove the paper protective film from the sealing putty.) After routing cables and
verifying cable connections, seal the gap between cables and the cabinet using sealing putty.
3. After verifying the installation, reinstall all the covers.
4. Do not remove the dustproof cover before power-on to prevent dust from entering the UPS.
2
(Perform this step only when the mains input and bypass input use different power
sources.) Remove the copper bars between the mains and bypass input wiring terminals.
Signal cable route
Monitoring
Interface Card
Equipotential
ground point
Mains input
Ambient
T/H Sensor
Bypass input
Dry Contact
Card
UPS output
Surge protection
boxes
Control module
NO connection
Intelligent
detection
board
Bypass modules
Paper
protective
film
Sealing putty
NC connection
Dustproof
cover