FusionDC1000A Prefabricated All-in-One Data Center V100R021C00 Commissioning Guide (IT Scenario) Issue Date 2021-04-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
About This Document About This Document Purpose This document describes how to power on and commission the FusionDC1000A prefabricated all-in-one data center solution (FusionDC1000 for short) in terms of safety precautions, preparations, power-on check, power-on commissioning, joint commissioning, power-off, and core device commissioning. It provides you a quick grasp of how to commission the prefabricated all-in-one data center.
The "NOTICE", "CAUTION", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements ● Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations. ●...
NO TICE To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ●...
CA UTION Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Switch on all SPD circuit breakers in the integrated UPS.
Step 1 (Skip this step in the case of ATS input.) Turn on the MCCB. Step 2 Turn on the UPS input circuit breaker QF1. The UPS is powered by the mains and initialization begins. The LCD displays the Huawei logo and an initialization progress bar. ----End Issue 01 (2021-04-20)
– After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
4.7.2.2 Obtaining the NetEco Software License The NetEco software license is not provided together with software to the customer. Therefore, obtain the NetEco software license in advance. Obtain the license from the Huawei's enterprise support website. ● For enterprise users: Log in to Huawei's enterprise support website https:// support.huawei.com/enterprise.
NE types and versions in Mapping Table . ● For carriers: Log in to Huawei's carrier support website https://support.huawei.com. Obtain iManager NetEco 6000 V600R021C00SPCXXX ReleaseDoc_ENG.zip, NetEco6000_V600R021C00SPCXXX_Adapters.zip, and NetEco6000_V600R021C00SPCXXX_DomainAdapters.zip from Support > Product Support > Carrier Cloud & Data Center > Data Center Facility >...