Step 8 In the lower-left corner of the page, click the Device tab.
Step 9 Click the drop-down list box in Type and select Sensor.
Step 10 In this example, a Polymer temperature and humidity (T/H) sensor is added in the
equipment room of the root node. Select the device to be added and drag its icon
to the management domain.
Step 11 Click the device. In the device parameter area on the right, set device parameters.
Step 12 Click
Step 13 Choose System > Service Settings > Management > Transmission Channel
Management.
Step 14 Click Modify after selecting the IP address of the ECC800-Pro connected to the
NMS.
Figure 4-13 Page for managing transparent transmission channels
----End
Issue 01 (2021-04-20)
NO TE
IP Address indicates the ECC800-Pro login IP address. Port indicates the ECC800-Pro COM2
port (3212). Device Address indicates the Polymer T/H sensor address.
to save the created device view.
If Connection mode is set to Compatible, click Confirm.
NO TE
– On the ECC800-Pro WebUI, set Enable Security Authentication to Disable.
– In transparent transmission channel management settings, the compatibility mode
has security risks. You are advised to select the security protocol mode.
If Connection mode is set to Security protocol, enter the value of Confirm
password that has been set on the ECC800-Pro WebUI, and click Confirm.