FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
Procedure
Step 1 On the UPS LCD screen, set System Info > Settings > Battery Settings > Battery
Type to Lithium battery.
The UPS software needs to be upgraded to the version that supports lithium
battery connection. See
the version number.
Step 2 Press and hold the POWER ON/OFF button on the BCU for more than 2s. The
green indicator of the BCU blinks at short intervals.
● The BCB off alarm (the red indicator is steady on) is displayed on the UPS LCD
and SmartLi LCD. No action is required. After the battery circuit breaker is
switched on, the alarm is automatically cleared.
● The green indicator blinks intermittently. After 1 minute, the BCU starts. The
green indicator blinks at super short intervals and the red indicator is steady
on.
● If multiple SmartLi cabinets are combined, press and hold the POWER ON/OFF
button on the BCU of the master cabinet for more than 2s to power on the
master cabinet. Then, power on slave cabinets one by one in the same way.
Step 3 Set the language, time, date, network parameters, and system parameters on the
Settings Wizard screen of the SmartLi.
Issue 01 (2021-04-20)
NO TICE
UPS5000 The Relationship of Software Version to check
NO TICE
Copyright © Huawei Technologies Co., Ltd.
4 Commissioning Core Devices
28

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents