Verifying The Settings - Hitachi Relion 670 Series Commissioning Manual

Bay control
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Section 11
Testing functionality by secondary injection
11.7.4.1

Verifying the settings

Time measurement and the injection of current and voltage can be done using a common test
equipment.
Verification of the START value and time delay to operation
1.
Connect the test set for the injection of three-phase currents and three-phase voltages to the
appropriate current and voltage terminals of the IED.
2.
Ensure that the settings in the IED are appropriate, especially the CurrStartLevel, FreqHighLimit,
FreqLowLimit, UHighLimit and ULowLimit setting.
3.
Supply the IED with three-phase currents and voltages at their rated value.
4.
Slowly decrease the frequency of the applied voltage until it crosses the frequency high limit and
the START signal appears.
5.
Check that the FREQOK signal appears.
6.
Compare the operate value to the set frequency high limit value.
7.
Decrease the frequency of the applied voltage until it crosses the frequency low limit and the
START signal disappears.
8.
Check that the FREQOK signal disappears.
9.
Compare the reset value to the set frequency low limit value.
10. Readjust the frequency of the applied voltage (with steps of 0.001 Hz/s) to a value within the set
frequency band limit.
11. Ensure that the START signal reappears.
12. Wait for a time corresponding to tCont and ensure that the TRIP and TRIPCONT signals are
generated.
13. Measure the time delay for the TRIP signal and compare it to the set value.
Verification of the ACCALARM value and time delay to operation
1.
Connect the test set for the injection of three-phase currents and three-phase voltages to the
appropriate current and voltage terminals of the IED.
2.
Ensure that the settings in the IED are appropriate for the default settings, especially the
CurrStartLevel, FreqHighLimit, FreqLowLimit, UHighLimit and ULowLimit setting.
3.
Supply the IED with three-phase currents and voltages at their rated value.
4.
Slowly decrease the frequency of the applied voltage until it crosses the frequency high limit and
the START signal appears.
5.
Continuously change the frequency of the applied voltage, so that for a certain time the
frequency is outside the set band limit and falls gradually within the band limit.
6.
Count only the time when the frequency lies within the set frequency band limit. Wait for a time
corresponding to tAccLimit and ensure that the ACCALARM signal appears.
7.
Measure the time delay for the ACCALARM signal and compare it to the set value.
Extended testing
1.
To check the value of TRIPACC, repeat the above test case in such a way that the frequency of
the applied voltage is within the set frequency band when time approaches the tAccLimit setting
value.
Verification of generator start and stop logic
1.
Ensure that the settings in the IED are appropriate to the default settings, especially the
CurrStartLevel, FreqHighLimit, FreqLowLimit, UHighLimit and ULowLimit.
2.
Ensure that the setting CBCheck is enabled.
3.
Supply the IED with three-phase currents and voltages at their rated values.
4.
Slowly decrease the frequency of the applied voltage until the START signal appears.
5.
Activate the CBOPEN input signal.
6.
Slowly decrease the injected current below the CurrStartLevel value until the START signal
disappears.
7.
Compare the current magnitude value to the set value.
146
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 511 403-UEN Rev. L
GUID-864636E0-6399-44E1-BD2C-C2113FB78C61 v3
Bay control REC670
Commissioning manual