Commissioning and maintenance of the fault clearing system
13.2.2.8

Restoring

Maintenance is very important to improve the availability of the protection system by detecting
failures before the protection is required to operate. There is however little point in testing healthy
equipment and then putting it back into service with an open terminal, with a removed fuse or open
miniature circuit breaker with an open connection, wrong setting, and so on.
Thus a list should be prepared of all items disturbed during test so that all can be put back into
service quickly and without overlooking something. It should be put back into service item by item
and signed by the responsible engineer.
216
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 511 403-UEN Rev. L
SEMOD56528-36 v2
Bay control REC670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rec670

Table of Contents