Conductor Routing and Grounding
1. Use separate metal conduits for routing the input power, output power, and control circuits.
2. Follow the wire size and tightening torque specifications in the UPS Installation Manual.
3. Always ground the unit to reduce the potential for electrical shock and to help reduce electrical noise.
4. A separate ground cable should be run inside the conduit with the input power, output power, and control circuits.
NOTICE
Cabinets must be properly grounded to Earth.
Improperly grounded cabinets my cause non-warrantable damage to equipment.
7.4
Anchorage
Once unpacked and moved to final location, install the ESS using the four holes in the channel base. Anchor the unit us-
ing appropriate hardware. Reference Figure 7.1 for base dimensions and anchoring hole details..
FIGURE 7.1: BOTTOM VIEW OF SCIB ESS
19
288V SCiB Energy Storage System Installation and Operation Manual – 203810-000