Seismic Anchorage - Toshiba 288V Installation And Operation Manual

Scib energy storage system
Table of Contents

Advertisement

7.5

Seismic Anchorage

1. Prepare the wall anchorages. Key measurements off the final installation location.
(Figure 7.2)
2. Assemble the fastener group (3/8" x 1.0" Long Bolt, Lock Washer + Flat Washer).
(Figure 7.3)
3. Secure the Top Seismic Bracket to the top rear of the UPS using two (2) fastener
groups. Skip this step if the bracket is pre-installed. (Figure 7.4)
4. Secure the Top Seismic Bracket to the wall anchors prepared in Step 1. (Figure 7.4)
FIGURE 7.4: TOP SEISMIC BRACKET INSTALLATION
Value
S
(z/h=1)
DS
S
(z/h=0)
DS
I
P
Values apply to both standalone or a group of modules with or without being physically connected together.
1
20
3
4
4
Seismic Specifications
Floor & Wall Mounted
1.06g
1.70g
1.5
288V SCiB Energy Storage System Installation and Operation Manual – 203810-000
5 in (127 mm)
3
FIGURE 7.2: SEISMIC ANCHORAGE
FIGURE 7.3: FASTENER GROUP
(BOLT +LOCK WASHER + WASHER)
1
Floor Mount Only
0.53g
0.85g
1.5
5.95 in
(151 mm)
3/8" Bolt
Anchor (2)
- WALL PATTERN
a
b
c

Advertisement