Verifying Hardware Installation - Huawei PDU8000 Quick Installation Manual

Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

4. Connect the UPS input and output power cables.
Rear view
To the UPS input terminal block
5. To separate strong-current cables
from weak-current cables, route
the signal cables upwards along
the rack rail through the holes
reserved at the outer side.
NOTE
The actual number of cables to be
connected and the positions vary
depending on the project design.
6
Check Before Power-On Commissioning

Verifying Hardware Installation

6.1
No.
Check Item
1
The PDC is clean and free of dust, dirt, and foreign matter.
2
The paint on the cabinet exterior is intact.
3
The cabinet door and lock work properly.
4
All safety marks and warnings are correct, clear, and complete.
There is no adhesive tape, cable tie, paper scrap, or packing
5
material around the cabinet.
Front view
13
Rear view
To the UPS output terminal block
Check Result
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail