Checking Electrical Connections; Checking Cable Installation; Power-On Commissioning - Huawei PDU8000 Quick Installation Manual

Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

Checking electrical connections

6.2
No. Check Item
1
All cables are connected correctly.
2
Ground cables are securely connected.
Power cables and ground cables are not coiled and extra parts are
3
cut off.
4
The phase sequence is correct.
Power cables and ground cables are routed and bound separately
5
from other cables.
6
All circuit breakers are OFF.

Checking Cable Installation

6.3
No.
Check Item
All bolts are tightened, especially the bolts used for electric
1
connection. Flat washers and spring washers are installed properly.
Cables are bound neatly, and cable ties are secured evenly and
2
properly in the same direction.
Cables are routed in a way convenient for maintenance and capacity
3
expansion.
4
There is no unnecessary adhesive tape or cable tie on cables.
Exposed parts of wires and cable lugs near the wiring terminals are
5
wrapped by insulation tape or heat shrinking tubing.
The routing of power cables and monitoring cables meets the
6
requirements for routing signal cables and power cables and complies
with the cable routing planning.
7

Power-On Commissioning

NOTICE
1. The power-on commissioning personnel must be at least two qualified electricians. One performs
operations while the other monitors the operations. Irrelevant persons should be warned off.
2. Powering off the PDC disconnects the power supply to the downstream devices. Exercise caution
with this operation when the PDC is supplying power to a working system.
3. If the power indicator on the front panel of the PDC lights up, the PDC is powered on properly.
1. Check cable connections and the mechanical performance.
Check that cables are connected correctly outside the cabinet. Check that all bolts are
secured for cables and tighten a bolt if it is loose.
Check that ground cables are properly connected.
(Optional) Switch on and off all circuit breakers and ATSs three times. Ensure that they can
be switched on and off smoothly.
14
Check Result
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
Check
Result
□Pass
□Fail
□Pass
□Fail
□Pass
□Fail
□Pass
□Fail
□Pass
□Fail
□Pass
□Fail