ISSUE 4.1 (R5.1)
1.4 Grounding and AC Cabling
The ETH (Earth Ground Lug) is located near the power supply on the KSU. The Sub-Cover must be
opened in order to access to it.
1.4.1 Grounding the KSU
Ensure Main KSU are powered off and unplug the AC cord.
In the KSU, connect the ETH lug to the verified grounding point using a minimum cable size of
14AWG (Φ2.0 mm) wire.
Screw
ETH Lug
• The grounding cable is supplier-provided.(not attached to the system)
1.
Loosen the screw.
2.
Insert a grounding wire (user supplied).
3.
Tighten the screw.
4.
Connect the grounding wire to earth ground.
Proper grounding is very important to protect the system from external
noise and to reduce the risk of electrocution in the event of a lightning
strike.
1.4.2 AC Power Requirement
A dedicated 100V-120V/220V/230V/240V 50/60Hz circuit located within two meters of the KSU is
required. A separate dedicated AC outlet is necessary for the KSU.
Double Pole/Neutral Fusing
(Power supply fuses are located at both the L and N side.)
Power Requirement
Power Consumption
Input Voltage (Rated Voltage)
Hardware Manual
To Earth
Figure 2-10 ETH Lug
Table 2-3 Power Requirement
110VAC
120VAC
110 VAC@15 A 120 VAC@15 A 220 VAC@15 A 230 VAC@15 A 240 VAC@15
Main KSU =
Main KSU =
128 VA
130 VA
90 VAC to 264 VAC (100VAC/120VAC/220VAC/230VAC/240VAC)
220VAC
230VAC
Main KSU =
Main KSU =
154 VA
154 VA
SL1100
240VAC
A
Main KSU =
156 VA
2-7