Cable Entry - ABB TZIDC Commissioning Instructions

Electro-pneumatic positioner for 4...20 ma two-wire technology, hart, profibus pa, foundation fieldbus
Hide thumbs Also See for TZIDC:
Table of Contents

Advertisement

Electrical connections
4.3

Cable entry

IMPORTANT (NOTE)
The cable terminals are delivered closed and must be unscrewed before inserting the cable.
For the cable entry into the housing, on the left-hand side of the housing there are two tap holes
in four thread combinations to accommodate the cable entry and pneumatic connection.
- Cable: thread 1/2-14NPT, air pipe: thread 1/4-18 NPT
- Cable: thread M20 x 1,5, air pipe: thread 1/4-18 NPT
- Cable: thread M20 x 1,5, air pipe: thread G 1/4
- Cable: thread G 1/2, air pipe: thread Rc 1/4
As an option, one thread can be fitted with a cable gland and the other with a pipe plug if
necessary.
Fig. 19: Cable entry
1 Pipe plug
2 Cable gland
24
TZIDC, TZIDC-110, TZIDC-120
CI/TZIDC/110/120-EN