Commissioning
10.1
Overview
Introduction
This section includes information on the following topics:
● Check before powering on for the first time
● Removing/inserting the SIMATIC memory card
● First power-on of the CPU
● Commissioning the ET 200MP for PROFINET IO
● Commissioning the ET 200MP for PROFIBUS DP
● Operating modes of the CPU
● CPU memory reset
● Identification and maintenance data
Commissioning requirements
Note
Performing tests
You must ensure the safety of your plant. You therefore need to perform a complete
functional test and the necessary safety checks before the final commissioning of a plant.
Also allow for any possible foreseeable errors in the tests. In this way, you avoid
endangering persons or plants during operation.
142
10
Automation system
System Manual, 12/2014, A5E03461182-AC