CHAPTER 4
This chapter describes the procedure from module mounting/connecting to system operation.
Checkbox
Master module mounting/connecting
Mount or connect the master module.
Slave module installation
Install the slave module in the control panel or machine.
Connect each module using transmission lines (DP, DN) and power
cables (24V, 0V).
System power-on
Check the following before powering on the system:
Whether the master module is properly mounted or connected
Proper voltage supply to the power supply module of the programmable
controller and 24V and 0V terminals of the master module
Whether the switch on the CPU module is set to STOP
Whether each module is properly wired
Transmission distance
Address setting
Set the address of the slave module.
PROCEDURES BEFORE OPERATION
Start
Wiring
CHAPTER 4 PROCEDURES BEFORE OPERATION
User's Manual (Hardware
Design, Maintenance and
Inspection) for the CPU
module used
MELSEC-L CC-Link IE Field
Network Head Module User's
Manual
User's manual for the slave
module used (manufactured by
Anywire Corporation)
Page 43, Section 6.2
Page 51, Section 6.4
Page 55, Section 7.2
4