Figure 5-5 Securing the PDC
----End
5.4.4 Installing the PDC on an ESD Floor
Context
Support is required when the PDC is installed on an ESD floor inside an equipment room. The
support height depends on the height between the ground and the ESD floor.
Procedure
Step 1 Lift the PDC onto the support and align the mounting holes in the PDC with those in the
support.
Step 2 Level the PDC by adjusting the anchor bolts, as shown by (1) in
Step 3 Insert four M12 bolts with spring washers and flat washers into the mounting holes for the
support and PDC, and partially tighten the bolts, as shown by (2) in
Issue 01 (2016-03-04)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installation Guide
Figure
5-6.
Figure
5-6.