Huawei NetCol5000-C Series User Manual page 103

In-row chilled water smart cooling product
Hide thumbs Also See for NetCol5000-C Series:
Table of Contents

Advertisement

NetCol5000-C(065, 080) In-row Chilled Water Smart
Cooling Product
User Manual
Figure 4-25 Checking before startup
Step 3 Tap Yes for check items one by one according to the prompt messages on the screen.
Step 4 Tap Yes and enter the screen where you select commissioning items, as shown in
Figure 4-26 Selecting commissioning items
Step 5 Tap Yes. The component startup commissioning screen is displayed, as shown in
Issue 07 (2020-03-16)
If the system is not configured with the humidifier components, the humidifier commissioning items
will not appear on the screen.
If the humidification function are disabled, you cannot select the humidifier item.
All the items are selected by default if you first enter the screen where you select commissioning
items. Except that the indoor fan item is mandatory, you can clear other commissioning items that
are not required.
Copyright © Huawei Technologies Co., Ltd.
4 Commissioning
Figure
4-26.
Figure
4-27.
95