5 Commissioning the BTS (Transmission Unavailable)
Figure 5-14 Site Configuration dialog box (3)
Step 4 Click Add Subobject. In the Object Attributes area, specify Object No., Object Name, Board
No., and Pass No.. Carrier0 is added in the Object Operation area. The carrier is bound to
pass 0 of the TRX whose board number is 0, as shown in
carrier A. The number of paths at an RFU depends on the number of carriers configured for the
RFU.
5-14
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
BTS3900(A) GSM
Commissioning Guide
Figure
5-15. Pass 0 is also called
Issue 02 (2009-04-20)