4 Commissioning the BTS (Transmission Available)

Figure 4-16 Query Board Running Software Version dialog box

Step 3 If the software version is correct, end this task. If the software version is incorrect, update the
software version through the loading and activation function of the LMT. For details, see the
BSC LMT User Guide.
----End
4.3.3 Checking the Consistency Between Hardware Installation and
Data Configuration
This describes how to check the consistency between hardware installation and data
configuration. The consistency is confirmed by checking the configuration and board status on
the LMT.
Context
l
l
l
4-14
CPRI connections: The port numbers SFP0 to SFP5 in the RXU topological structure area
on the LMT correspond to the ports CPRI0 to CPRI5 on the panel of the BBU.
Slots for the RFUs: On the LMT, the RFUs are configured in subrack 3. The slot numbers
of the RFUs are based on the configuration sequence of the TRXs, starting from slot 0. In
actual installation, the installation slot of the RFU is determined by the actual requirements.
The relations between the data configuration and the physical connections of monitoring
boards connected to RS485 ports are described as follows:
Figure 4-17
shows the relation between data configuration and physical connection of
the BTS3900 monitoring boards.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
BTS3900(A) GSM
Commissioning Guide
Issue 02 (2009-04-20)