Advertisement

3 Commissioning Process
Step 3 Specify the values of the parameters.
For detailed explanation of the parameters, see the online help.
For example: DSP CBTSCFG: BTSNAME="BTS", BTSID=1, CFGID=CBTSINFO;
Step 4 Click
----End
3.4.7 Verifying the Consistency of the Configuration Data
Between the BTS and the BSC Interface
To verify the consistency of the configuration data between the BTS and the BSC interface,
do as follows:
Step 1 Enter the command CHK CBTSIFCFG.
Step 2 Click
Step 3 Specify the values of the parameters.
For detailed explanation of the parameters, see the online help.
For example: CHK CBTSIFCFG: BTSID=1, CFGINFO=ALL;
Step 4 Click
----End

3.4.8 Querying the Status of the BTS Links

To query the status of the BTS links, do as follows:
Step 1 Enter the command DSP CBTSLNKSTAT.
Step 2 Click
Step 3 Specify the values of the parameters.
For detailed explanation of the parameters, see the online help.
For example: DSP CBTSLNKSTAT: BTSID=1, BRDID=0;
Step 4 Click
----End

3.5 RF Performance Test

The RF performance test consists of:
3-20
or press F9 to execute the command.
or press Enter.
or press F9 to execute the command.
or press Enter.
or press F9 to execute the command.
Forward power test
Reverse RSSI test
Huawei Technologies Proprietary
Airbridge BTS3606E&3606AE
System Commissioning Guide
Issue 02 (2006-10-10)