Figure 3-8 Connection For Forward Power Test - Huawei Airbridge BTS3606E Commissioning Manual

Table of Contents

Advertisement

3 Commissioning Process

Figure 3-8 Connection for forward power test

CDDU
cabinet top
Step 2 In the Windows operating system of the LMT, select Start > Run, type Telnet
xxx.xxx.xxx.xxx in the Run dialog box, and then press Enter to start Telnet.
Step 3 Start the power test for the BTS transmitting at full power.
For example, for the 450A carrier, execute the following commands:
HW CBTS>str trmpowertst:brdid=2,chid=0,channo=210
Are you sure?(Y or N)y
Ok
HW CBTS>str trmpowertst:brdid=2,chid=1,channo=160
Are you sure?(Y or N)y
Ok
HW CBTS>str trmpowertst:brdid=2,chid=2,channo=260
Are you sure?(Y or N)y
Ok
Step 4 After preheating the BTS for ten minutes, check the output power that is displayed on the
power meter and record the value.
Step 5 Analyze the test result.
See section 3.5.2 "Forward Power Test Analysis."
If the result is abnormal, handle the situation according to section 3.5.2 "Forward Power Test
Analysis."
3-22
BTS
For the near end Telnet, the default IP address of the Ethernet port is 172.16.16.16.
"chid" is the ID of a carrier provided by the TRM. The IDs of the carriers provided by the
CMTR/OMTR are 0, 1, and 2.
"channo" is the center frequency of the carrier.
You must test the powers of the three carriers of the CMTR/OMTR at the same time.
Huawei Technologies Proprietary
-
TX2/RX2
ANT
-
TX2/RX2
TEST
-
TX1/RX1
ANT
TX1/RX1 - TEST
Power
meter
Airbridge BTS3606E&3606AE
System Commissioning Guide
Antenna
Issue 02 (2006-10-10)

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Airbridge bts3606ae

Table of Contents