Prerequisites
Ensure that the installation floor is level.
Procedure
Step 1 Install the cabinet.
1.
2.
3.
4.
Figure 6-4 Installing a cabinet
----End
Issue 01 (2020-11-30)
Determine the mounting holes for the cabinet based on the marking-off
template. A indicates the mounting holes for channel steel. B indicates the
mounting holes for the floor. The unit is mm.
Drill holes and install expansion sleeves.
Secure the cabinet to the floor.
Install anchor baffle plates.