Installing The Ac Input Power Cable - Huawei SmartACBox-12/1-JP User Manual

12-in 1-out smart ac combiner box
Table of Contents

Advertisement

SmartACBox 12-In 1-Out Smart AC Combiner Box
User Manual

5.8 Installing the AC Input Power Cable

Prerequisites
The AC input power cable and OT-M5 terminal are available.
Context
Connect the AC input power cable from the SmartACBox to input circuit breakers QF01 to
QF12. Recommended: Route the AC input power cables to input circuit breakers QF01 to
QF06 through cable hole 1; route the AC input power cables to input circuit breakers QF07 to
QF12 through cable hole 2.
Procedure
Step 1 Remove an appropriate length of the jacket and insulation layer from the AC input power
cable using a wire stripper.
Figure 5-12 Stripping an AC input power cable
(1) Core wire
Step 2 Crimp an OT terminal.
Step 3 Route the cables through the cable holes 1 and 2 for the AC input power cable.
Step 4 Connect the AC input power cable to the U, O, and W terminals on the circuit breaker, and
tighten the bolts using a torque screwdriver.
Issue 03 (2018-05-15)
The lengths of the jackets and insulation layers that need to be removed from the AC input
power cables to input circuit breakers QF01 to QF06 are different. When connecting a
stripped cable, ensure that the exposed insulation layer is all in the enclosure, and the
jacket is all outside the enclosure.
For the lengths of the jackets and insulation layers that need to be removed from the AC
input power cables to input circuit breakers QF07 to QF12, refer to the AC input power
cables to input circuit breakers QF01 to QF06.
Copyright © Huawei Technologies Co., Ltd.
(2) Insulation layer
5 Electrical Connections
(3) Jacket
41

Advertisement

Table of Contents
loading

Table of Contents