Huawei FusionDC1000A Quick Manual page 13

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:

Advertisement

Note:
1. The rain and snow cover is secured to the pre-fab. module using three
GB9074_17-88_M10X40_S_ZNAL screws to a torque of 40 N·m. The preceding figure shows the
positions for securing the cover
.
1
.
Remove the four GB9074_17-88_M10X40_S_ZNAL screws if
there is are eaves for the delivered pre-fab. module. Remove the
eaves and install the cover after cleaning eaves.
2. Secure cover component 2 to the pre-fab. module using three
GB9074_17-88_M10X40_S_ZNAL screws, and then assemble cover components 1
and 2 using two GB9074_17-88_M10X40_S_ZNAL screws to a torque of 40 N·m
.
No.S008 (Optional) Rain And Snow Cover Installation Positio
Name
Drawing No.
Qty Unit
Screw
GB5783-2000_M12×30_S_ZNAL
5
PCS
Rain and snow cover
DKBA61545321
1
PCS
Rain and snow
cover component 1 DKBA61568040
1
PCS
Rain and snow
cover component 2 DKBA61545321
1
PCS
Apply sealant on the top of the rain and snow cover after it is installed.