3
Installing Power Supply and Distribution Devices
3.1
Installing Lithium Batteries
1. Push a lithium battery into the
cabinet and secure it.
Install lithium batteries in the 11th U and
higher positions of the cabinet.
3.3
(Optional) Installing Busbars
4
Installing Monitoring Devices
4.1
Installing the SIM Card and Antenna
1. Remove the ECC800-Pro main control module.
2. Install the SIM card.
12.1
3.2
Install Busbars
Install rPDUs in the 11th U and 13th U
positions of the rear door of the cabinet.
If there is more than one lithium
battery, install busbars.
The busbars need to be installed 2
U above the last lithium battery.
Determine the busbar installation
position based on the lithium
battery configuration.
3. Attach the antenna to the middle of the
cabinet top.
4. Connect the antenna cable.