4.2
Installing a PAD
1. Adjust the PAD mounting support to match the dimensions of the PAD to be installed.
2. Remove the nuts from the PAD mounting support and install the support.
3. Route the PAD power cable through the cable hole and connect the cable.
4. Clamp the PAD.
5. Connect the ECC800-Pro USB cable to the charging port on the PAD.
Adjusting
screws
4.3
Installing T/H Sensors
Installing Remote T/H Sensors for
Smart Cooling Products
1. Unpack the two T/H sensors. Attach one
sensor to the right post at the 33th U
position on the front door and the other
to the right post at the 11th U position
on the rear door of the cabinet.
2. Set the DIP switch address of the T/H
sensor on the front door to 2 and that
of the T/H sensor on the rear door to 1.
3. Insert the pre-routed cables into the
ports on the T/H sensors on the front
and rear doors.
The installation positions of the T/H sensors can be adjusted as required.
The default device address is 1.
Installing an Electrode
4.4
Water Sensor
1. Place the water sensor on the floor
under the cabinet.
2. Route the water sensor cable through
the cable hole at the bottom of the
cabinet, and connect the cable to the
water sensor cable connected to the
ECC500.
3. Install the water detector.
Installing Cabinet T/H Sensors
1. Unpack the two T/H sensors and attach
one sensor to the mounting bars at the
39th U position on the front door and the
other to the 37th U position on the rear
door of the cabinet.
2. Set the DIP switch address of the T/H
sensor on the front door to 2 and that of
the T/H sensor on the rear door to 1.
3. Insert the pre-routed cables into the
ports on the T/H sensors on the front and