2.1
Preparing an Indoor Unit Base
1. Shock absorption bars (EPDM rubber, 5 mm
thick) need to be installed between the
ground and the base.
2. The base should be at least 250 mm in
height. The base bearing capacity must be
at least 2 t.
3. You are advised to use angle steel, square
steel or channel steel. Thickness of 3 mm to
5 mm is recommended.
2.2
Holes in Top and Bottom Plates
(Top view of the bottom plate)
Front
Rear
3

Installing the Equipment

NetCol5000-C(030, 032, 065) In-row Chilled Water Smart Cooling Product User
1. Read the
Manual (2019)
or instructions before installing the NetCol5000-C.
2. You are recommended to use tools that are fully insulated when installing devices.
3. Only engineers from the manufacturer or engineers certified by the agent are allowed to
install, commission, and maintain smart cooling products. Otherwise, personal injuries and
device damage may be caused, which is beyond the smart cooling product warranty range.
Unit: mm
(Top view of the top plate)
2
Unit: mm
(1) Equipotential PE cable
hole (Φ28 mm)
(2) Drainpipe hole (Φ43 mm)
(3) Humidifier water inlet
pipe hole (Φ43 mm)
(4) Chilled water inlet pipe
hole (Φ103 mm)
(5) Chilled water outlet pipe
hole (Φ103 mm)
(6) Power cable hole (Φ43
mm)
(7) Signal cable hole (Φ43
mm)