Huawei FusionDC1000A Quick Manual page 11

Prefabricated modular data center
Hide thumbs Also See for FusionDC1000A:

Advertisement

NO.S002 Site Space and Pre-fab. Module Installation Position Diagram
Concrete platform
Single-capacity base
Concrete platform
Ground
Concrete platform
Concrete platform
Note:
1. The concrete platform needs to support a pre-fab. module with the maximum weight of 25,000 kg. The recommended
area of a single-capacity base installed on the ground). Take an engineering margin into consideration.
2. Each base has eight mounting holes. You need to install only four holes (preferably the outer four holes). If an outer hole is on
the top of groundwork reinforcing steel bars, select the inner hole instead.
3. During installation, ensure that the direction of the single-capacity base is the same as the drawing.
4. Reserve two cable outlets for power cables at the shown positions on the ground. It is recommended that the cable outlets be