Battery Pack Installation
4.8 Finalizing installation
Follow these steps to finalize the installation.
1. Stuff the small grommets left unused with an insulating material like silicone sealant, and
then push them into the remaining holes.
2. Apply silicone sealant or putty around the cable at each grommet to prevent foreign
materials from entering the battery pack.
3. Check if the configuration switches are set properly, referring to Configuring Battery
pack on page 36.
4. Turn on the battery pack as described in Commissioning battery pack on page 40.
5. Replace the top cover and tighten the screws to a torque of 5 N·m.