3. Wait for transition to warming-up phase:
When the splash screen disappears, the device is in the warming-up phase. The current
warm-up progress is indicated by a bar chart in the dialog window.
4. Call up the measured value display during the warm-up phase:
– Close the warming-up window by pressing <ENTER>.
Setting up
Note
Operator control options
When commissioning for the first time, two methods can be used. You can use the menu
"[1] Quick Start" to start the device with the simplified process or opt for the more detailed
procedure.
For information on the simplified procedure "Quick Start" refer to the operating instructions.
Make the necessary settings in the appropriate submenus.
SIPROCESS GA700 rack and wall mounted devices
Compact Operating Instructions, 06/2023, A5E35134047-AB
The display shows the measured-value display in read mode.
For the duration of the warming-up phase, the device is in "Function check" mode. The
following symbol is displayed in the status bar:
Commissioning
5.5 Local commissioning
79