5.4.3 Installing the Battery in the Extinguishant Control Panel

Prerequisites
● The extinguishant control panel has been configured and commissioned before
● Non-professional personnel are prohibited from operating the Write Enabler
● You are advised to power on the battery within 24 hours after unpacking. If the
Issue 15 (2023-11-01)
NO TICE
delivery. Non-professional personnel are prohibited from configuring the
extinguishant control panel without permission.
button.
battery cannot be powered on in time, place it in a dry indoor environment
without corrosive gases.
NO TE
● The battery is delivered with the product and can be obtained from the control unit
cabin. If it needs to be replaced, purchase a battery according to the specifications in
2.6.4.4 Extinguishant Control
● If a battery is damaged, contact your local office.
Determine the position of the extinguishant control panel.