6.5.2 Installing Extinguishant Control Panel Batteries

Prerequisites
The pre-fab. modules have been installed.
Context
The fire control panel battery has been installed before delivery. You only need to connect the
reserved cable to the battery onsite.
Preparations
Tools: protective gloves
Materials: extinguishant control panel batteries
Skill requirement: common technician
Procedure
Step 1 Open the door of the extinguishant control panel, and install batteries in the reserved position.
Issue 02 (2020-01-15)
Remove the protective cover at the electrical actuator installation position on the
container valve. Align the electrical actuator and the container valve, and tighten the
electrical actuator clockwise.
Connect the cables between the electrical actuator and the extinguishant control panel.