Preparing Cable Terminals - Huawei FusionModule1000A20 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Material: label
Documents: none
Skill requirement: common technician
Procedure
Step 1 (Optional) Prepare labels based on site requirements.
Step 2 Select correct cable labels.
Step 3 Remove the simple labels attached to a cable during layout and attach the selected labels to
both ends of the cable.
----End
A.2 Preparing Cable Terminals
Preparations
Tools: hydraulic pliers, heat gun, and crimping tool
Materials: heat shrink tubing, DT terminal, OT terminal, and cord end terminal
Documents: none
Skill requirement: common technician
Procedure
Step 1
Figure A-15
Issue 02 (2020-01-15)
Label information must be clear and specific.
Labels must be easy to attach and can be securely attached.
Labels must be resistant to corrosion and deterioration.
Labels must be securely attached.
Labels must be attached in eye-catching positions on cables for ease of maintenance.
The labels on both ends of a cable must be the same.
shows how to prepare a DT terminal.
Copyright © Huawei Technologies Co., Ltd.
A A Basic Installation Operations
94