A.9 Preparing a Monitoring Cable
Prerequisites
Preparing a Cord End Terminal
Figure A-49 shows how to prepare a cord end terminal.
1.
2.
3.
Figure A-49 Preparing a cord end terminal
(A) Cord end terminal connector
Preparing an RS485 Monitoring Cable
Figure A-50 shows how to prepare an RS485 monitoring cable for the ECC collector.
Issue 04 (2017-06-30)
A network cable, cord end terminals, and RJ45 connectors are prepared.
The following tools are prepared:
Wire stripper
Crimping tool
RJ45 crimping tool
Electrician's knife
Insulation tape
Strip the insulation layer of cable B to expose cable core C.
Put cable core C through cord end terminal A.
Crimp the metal part of cord end terminal A using the crimping tool.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(B) Insulation layer
A Appendix
(C) Copper core wire
244

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents