Figure 7-5 Connecting power cables for the server
----End

7.3 (Optional) Installing a VCN500

Procedure
Step 1 Determine the mounting holes for the VCN500 based on the network cabinet device layout,
adjust the guide rails, and install floating nuts.
Step 2 Place the VCN500 into the network cabinet with caution, and gently press down buttons on
the mounting ears.
Issue 04 (2017-06-30)
The server uses dual power supplies. Connect the two power cables to different PDU2000s.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.