Connecting Cables to the Circuit Breaker in a Battery Cabinet
Before connecting cables, ensure that the circuit breaker is OFF.
Connect cables to the circuit breaker as follows:
1.
2.
3.
4.
5.
Issue 04 (2017-06-30)
Figure 10-28 Incorrect battery cable connection method
(Optional) If the intelligent battery monitoring system is deployed, knock off the cover
on the CIM indicator hole on the circuit breaker panel, as shown by (1) in Figure 10-29.
Remove the circuit breaker panel, as shown by (2) in Figure 10-29.
Connect the battery cables +, N, and -, as shown by (3) in Figure 10-29.
Connect the UPS cables +, N, and -, as shown by (4) in Figure 10-29.
(Optional) If two battery strings are deployed, connect the UPS terminals +, N, and - for
one battery string to the UPS terminals +, N, and - for the other battery string.