Huawei FusionModule2000 Installation Manual page 90

Smart modular data center, 2000 mm high cabinets, single-row aisle containment, 380 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Figure 4-8 Taking out PDU2000 industrial connectors
Step 2 Lay out the PDU2000 industrial connectors and cables on the cabinet top, and reinstall the
rodent-proof mesh.
Cut the rodent-proof mesh based on the cable thickness using a tool such as diagonal pliers. If
the opening is too large, unwanted things may fall into the cabinet through the opening.
Figure 4-9 Laying out PDU2000 industrial connectors and cables
Repeat the preceding steps to take out and preinstall PDU2000 industrial connectors for all cabinets.
----End
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Installing Cabinets
81

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents