Figure 7-52 Installing a pad
----End
7.8.6.7 Securing the Pad Mounting Kit
Procedure
Step 1 Lay out the cables of monitoring components on the pad mounting kit.
Step 2 Clamp the pad mounting kit to the hanging kit.
Step 3 Secure the pad mounting kit to the hanging kit using two M5x10 tapping screws.