3.2.3 Removing the NetCol5000-A 35 kW Air Conditioner Pallet

Procedure
Step 1 After a packed cabinet arrives onsite, unpack the cabinet.
Do not damage the cabinet exterior.
Step 2 Remove the M5 and M12 screws that secure the air conditioner to the pallet, and take off the
L-shaped brackets, as shown in Figure 3-26.
Figure 3-26 Removing the screws
Step 3 Remove the cabinet from the pallet.
----End

3.2.4 Removing the NetCol5000-A 25 kW Air Conditioner Pallet

Procedure
Step 1 Use a 10# socket wrench to remove the eight M6x16 screws securing the fasteners to the
cabinet, and use an 18# socket wrench to remove the four M12x35 screws securing the
fasteners to the pallet, as shown in Figure 3-27.
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
45

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents