FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
6

6.1 Installing a 600 mm Wide Cable Trough

Context
Install two 600 mm cable troughs on the top of every 600 mm wide cabinet. Install two cable
troughs on the top of PDCs first, and then install cable troughs on the top of other cabinets
along the aisle in sequence.
Figure 6-1 shows a 600 mm wide cable trough. Its BOM number is 21501142.
Figure 6-1 600 mm wide cable trough
(1) Partition plate
When installing cable troughs, be aware of PDU2000 cables and industrial connectors on the
top of cabinets:
Issue 04 (2017-06-30)

(Optional) Installing Cable Troughs

Cold aisle scenario: Install cable troughs above the front door of a cabinet first. When
installing cable troughs above the rear door, move the cables to the open area of the cable
troughs. After installing cable troughs above the rear door, place the PDU2000 cables
and industrial connectors inside the cable troughs above the front door. For details, see
Figure 6-2.
Hot aisle scenario: After cable troughs above the front and rear doors are installed, place
the PDU2000 cables and industrial connectors in the cable trough above the rear door.
After PDU2000 cables and industrial connectors are placed, bind the cables to the cable
trough using cable ties.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 (Optional) Installing Cable Troughs
(2) Vertical plate
(3) Tray
115