600 mm adjustable base
Procedure
Step 1 Mark holes for installing expansion bolts on the concrete floor by using a marker.
Step 2 Move the base, and drill holes to depths of 52 mm to 60 mm using a hammer drill with a Φ16
drill bit.
Step 3 Move back the base, and partially tighten the expansion bolts.
Step 4 (Optional) Put spacers under the base to level it.
Step 5 Reinstall the expansion bolt and tighten it.
Figure 3-60 Tightening an expansion bolt
Step 6 Install and secure other bases in the same way.
Step 7 Secure adjacent bases.
Issue 04 (2017-06-30)
A spacer may be 0.5 mm, 1.0 mm, or 2.0 mm thick.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
Securing Method
supports of the base, and secure the base to
the concrete floor using six expansion bolts.