Figure 3-23 Removing the L-shaped bracket
Ensure that the sliding plates are properly installed in step 2 in Figure 3-23. Otherwise, the sliding plates
may shift when the PDC is unloaded.
Step 7 Raise the four leveling feet using an adjustable wrench.
Figure 3-24 Raising the leveling feet
Step 8 Slide off the PDC and push it to the installation position.
----End
Issue 04 (2017-06-30)