FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
4.
Step 3 Close the front and the rear doors.
----End
3.2 Removing Pallets
3.2.1 Removing the PDC Pallet
Context
Issue 04 (2017-06-30)
Figure 3-22 Connecting the interconnection terminal
Reinstall the water pan cover.
To avoid personal injury, three to four persons need to work together when moving a
cabinet.
When moving a cabinet, verify that any open doors do not fall off.
The cabinet with castors can be slid off its pallet using the PDC sliding panel.