FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Figure 7-3 Installing guide rails
1.
2.
3.
Step 2 Place the server on the guide rails and slide it along the guide rails into the cabinet.
Step 3 Align the two mounting ears of the server with the rack rail of the cabinet and tighten the
screws on the mounting ears.
Figure 7-4 Installing the server
Step 4 Connect the server power cables to the PDU2000.
Issue 04 (2017-06-30)
Place the guide rails horizontally at the installation position in the cabinet.
Fix the guide rails using rubber plugs.
−
In front of the guide rails: If a server is installed using the upper mounting holes,
insert rubber plugs tightly into the holes at the middle. If a server is installed using
mounting holes at the middle, insert rubber plugs tightly into the upper holes.
−
Behind the guide rails: Insert rubber plugs tightly into the upper mounting holes.
(Optional) To enhance the rigidness and seismic-proof performance of a server, you can
install bolts at the rear of telescopic guide rails.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Installing Monitoring Devices
125