Figure 4-11 Installing a ground copper bar
----End

4.3.3 (Optional) Installing a Vertical Ground Copper Bar

Context
The BOM number for the vertical ground copper bar is 21241363.
Procedure
Step 1 Open the rear cabinet door, and secure the ground copper bar to the right rack rail by
installing four M4 screws respectively at the 04 U, 14 U, 29 U, and 39 U positions. Note that
a screw should be secured to the middle tapped hole of each U.
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.